Licence conditions for pollution studies and reduction program


  

Licence conditions for pollution studies and reduction programs

Summary
 
Licence number: 1767
Title: Capacity Assessment - Pollution Study
Start date: 27 Oct 2015
 
Licence Condition
The licensee must assess the effluent receipt, treatment and storage capacity of the Kurri Kurri wastewater treatment plant under all weather conditions  This assessment must include: identification of any works or actions necessary to ensure that the plant is capable of complying with the limit conditions specified in the licence; and estimates of the cost of any identified works or actions; and an indicative timetable for implementation of any identified works or actions. The licensee must submit a report detailing the findings of this assessment by 31 August 2016 to the EPA's Regional Manager, Hunter at hunter.region@epa.nsw.gov.au